Construction site of prefabricated houses


Release time:

2026-06-01

1. Material entry

1

 

2. Assembly of foundation embedded parts

1

 

3. Put on the line

1

 

4. Foundation treatment

1

 

5. Place embedded parts

1

 

6. Beam installation

1

 

7. Concrete pouring

1

 

8. Column installation

1

 

9. Ground structure board installation

1

 

10. Beam installation

1

 

11. Wall structure board installation

1

 

12. Installation of ground structural panels on the second floor

1

 

13. Column installation on the second floor

1

 

14. Beam installation on the second floor

1

 

15. Installation of wall structural panels on the second floor

1

 

16. Installation of structural panels on the roof of the second floor

1

 

17. Cement slab paving for exterior wall

1

 

18. Roof structure installation

1

 

19. Roof waterproof treatment

1

 

20. Roof metal tile paving

1

 

21. Wall decoration board paving

1

 

22. Sewer pipe installation

1

 

23. Ground concrete preparation

1

 

24. Ground concrete pouring

1

 

25. Asphalt tile laying

1

 

26. Window installation

1

 

27. Partition keel installation

1

 

 